Construction Blog

A look at the construction site

Every label represents added value for your stay. Whether it’s verified quality, a commitment to sustainability, or special services, our awards highlight what makes Hotel 6000 unique and what you can count on when you stay with us.

Webcam
Tribschenstrasse 7, 6005 Luzern
Work is now underway on multiple fronts simultaneously: on the 5th floor, the next walls and ceilings are scheduled for construction, and the precast concrete stairs leading up to the parapet have already arrived on site.
While the facade's substructure is being installed outside, work is also progressing steadily on the inside. Ventilation, plumbing, and electrical systems are being installed step by step, giving the hotel more and more of its technical infrastructure. Progress is also being made in the basement, where edge sealing between the floor and walls is currently underway.
In short: formwork is being set, components are being installed, systems are being laid, and waterproofing is being applied—the shell of the building is increasingly taking shape as a real hotel.
August 12, 2026

SOMETHING IS HAPPENING HERE

Work is now underway on multiple fronts simultaneously: on the 5th floor, the next walls and ceilings are scheduled for construction, and the precast concrete stairs leading up to the parapet have already arrived on site. While the facade's substructure is being installed outside, work is also progressing steadily on the inside. Ventilation, plumbing, and electrical systems are being installed step by step, giving the hotel more and more of its technical infrastructure. Progress is also being made in the basement, where edge sealing between the floor and walls is currently underway. In short: formwork is being set, components are being installed, systems are being laid, and waterproofing is being applied—the shell of the building is increasingly taking shape as a real hotel.

With the structural work nearing completion, the focus is shifting increasingly toward the facade and building services. The first support brackets for the facade have been delivered, and the surveying work is already underway. There is also plenty of activity inside the building: the initial ventilation systems have been installed, condensate lines are being laid in the wet rooms, and cable pulling is progressing steadily. This marks the start of an exciting new phase on the construction site: bit by bit, the hotel is taking shape, not only in its exterior appearance but also in its technical infrastructure.
August 3, 2026

BRINGING THE BUILDING TO LIFE

With the structural work nearing completion, the focus is shifting increasingly toward the facade and building services. The first support brackets for the facade have been delivered, and the surveying work is already underway. There is also plenty of activity inside the building: the initial ventilation systems have been installed, condensate lines are being laid in the wet rooms, and cable pulling is progressing steadily. This marks the start of an exciting new phase on the construction site: bit by bit, the hotel is taking shape, not only in its exterior appearance but also in its technical infrastructure.

Work on the construction site continues to reach new heights: the ceiling above the 4th floor has been poured, and the walls for the 5th floor are already taking shape. Formwork for the next ceiling is also well underway.

At the same time, work in the basement is progressing steadily. The concrete wall and both ramps are currently being reinforced, and the concrete restoration work is nearing completion.

Preparations for the facade are also moving forward: the necessary reference axes for future surveying have already been established from the 1st to the 4th floor.

As the building continues to rise, the next visible milestones are quickly coming into view.
July 22, 2026

AIM HIGH

Work on the construction site continues to reach new heights: the ceiling above the 4th floor has been poured, and the walls for the 5th floor are already taking shape. Formwork for the next ceiling is also well underway. At the same time, work in the basement is progressing steadily. The concrete wall and both ramps are currently being reinforced, and the concrete restoration work is nearing completion. Preparations for the facade are also moving forward: the necessary reference axes for future surveying have already been established from the 1st to the 4th floor. As the building continues to rise, the next visible milestones are quickly coming into view.

Construction is progressing rapidly on site: the ceiling above the 4th floor is being completed in stages, and the first walls are already taking shape on the 5th floor. This means the new hotel is continuing to grow significantly in height.

There has also been plenty of activity in the basement. Milling work for the ceiling replacement is complete, and preparations for the next phase are underway. At the same time, concrete renovation work has begun, and the reinforcements using CFRP strips have been successfully finished.

While the next floor is already taking shape up top, the final details are being addressed below—bringing the hotel one step closer to its final form.
July 1, 2026

GROWING ABOVE, REFINING BELOW

Construction is progressing rapidly on site: the ceiling above the 4th floor is being completed in stages, and the first walls are already taking shape on the 5th floor. This means the new hotel is continuing to grow significantly in height. There has also been plenty of activity in the basement. Milling work for the ceiling replacement is complete, and preparations for the next phase are underway. At the same time, concrete renovation work has begun, and the reinforcements using CFRP strips have been successfully finished. While the next floor is already taking shape up top, the final details are being addressed below—bringing the hotel one step closer to its final form.

The structural work is progressing according to schedule, and the future hotel continues to take shape. Construction of the first walls for the fourth floor is already well underway, while preparations for the building services are being carried out on the ceiling above the third floor.
Work in the basement is also being steadily completed. The masonry work is largely finished, and drilling and milling for the technical infrastructure are in full swing. At the same time, the installed construction drying system is already significantly reducing humidity, creating optimal conditions for the next stages of construction.
With every phase, the vision of the new hotel moves one step closer to reality.
June 11, 2026

THE HOTEL CONTINUES TO TAKE SHAPE

The structural work is progressing according to schedule, and the future hotel continues to take shape. Construction of the first walls for the fourth floor is already well underway, while preparations for the building services are being carried out on the ceiling above the third floor. Work in the basement is also being steadily completed. The masonry work is largely finished, and drilling and milling for the technical infrastructure are in full swing. At the same time, the installed construction drying system is already significantly reducing humidity, creating optimal conditions for the next stages of construction. With every phase, the vision of the new hotel moves one step closer to reality.

Another milestone has been reached: the structural shell has now almost reached the height of the treetops, and the future hotel is becoming an increasingly prominent feature of the construction site. While the ceilings above the second floor are being shuttered in the upcoming construction phases, the walls on the second floor are nearly complete. At the same time, the first walls of the third floor are already taking shape—the building continues to grow steadily upward.

Work in the basement is also progressing according to schedule. The final waterproofing is being completed, and the building drying process is already underway. In parallel, the pile-driving work has begun, and preparations for the next construction phases are in full swing. With every floor added, the future scale and shape of the new hotel are becoming increasingly clear.
May 21, 2026

WE WILL SOON REACH THE HEIGHT OF THE TREETOPS

Another milestone has been reached: the structural shell has now almost reached the height of the treetops, and the future hotel is becoming an increasingly prominent feature of the construction site. While the ceilings above the second floor are being shuttered in the upcoming construction phases, the walls on the second floor are nearly complete. At the same time, the first walls of the third floor are already taking shape—the building continues to grow steadily upward. Work in the basement is also progressing according to schedule. The final waterproofing is being completed, and the building drying process is already underway. In parallel, the pile-driving work has begun, and preparations for the next construction phases are in full swing. With every floor added, the future scale and shape of the new hotel are becoming increasingly clear.

The ceiling above the ground floor has been fully poured, marking the successful completion of the first level. Final touches, such as concrete finishing, are currently underway, while all walls on the first floor are already complete. Work has also begun on the second floor, where the next set of walls is taking shape step by step. At the same time, drilling and cutting work is in full swing in the basement. The building is steadily gaining both height and structure.
April 15, 2026

WE'RE TAKING OFF

The ceiling above the ground floor has been fully poured, marking the successful completion of the first level. Final touches, such as concrete finishing, are currently underway, while all walls on the first floor are already complete. Work has also begun on the second floor, where the next set of walls is taking shape step by step. At the same time, drilling and cutting work is in full swing in the basement. The building is steadily gaining both height and structure.

A major milestone has been reached: the majority of the ground floor walls and the ceiling above them have been successfully poured.
Work has already begun on the first floor—the first walls are taking shape, and all necessary materials are on-site. The weather is also currently playing along, supporting our rapid construction progress.
With every step, the new hotel is visibly rising.
March 11, 2026

The first floor is almost roofed

A major milestone has been reached: the majority of the ground floor walls and the ceiling above them have been successfully poured. Work has already begun on the first floor—the first walls are taking shape, and all necessary materials are on-site. The weather is also currently playing along, supporting our rapid construction progress. With every step, the new hotel is visibly rising.

The concrete walls in the basement are now fully complete – another major milestone in the structural shell construction.
At the same time, formwork has begun above the ground floor. The precast concrete stairs between the basement and ground floor have also been successfully installed, now visibly connecting the two levels.
Waterproofing in the basement is largely finished, allowing the building to continue rising on schedule.
February 25, 2026

From the basement to the top – the next stages are underway

The concrete walls in the basement are now fully complete – another major milestone in the structural shell construction. At the same time, formwork has begun above the ground floor. The precast concrete stairs between the basement and ground floor have also been successfully installed, now visibly connecting the two levels. Waterproofing in the basement is largely finished, allowing the building to continue rising on schedule.

Work on the construction site is back in full swing. Currently, the focus is primarily on essential snow removal. The first concrete wall on the ground floor is scheduled to be poured later this week, followed by the concrete walls for the basement and upper floors in the coming weeks.
Step by step, the new hotel is now visibly taking shape.
January 6, 2026

LET'S GO

Work on the construction site is back in full swing. Currently, the focus is primarily on essential snow removal. The first concrete wall on the ground floor is scheduled to be poured later this week, followed by the concrete walls for the basement and upper floors in the coming weeks. Step by step, the new hotel is now visibly taking shape.

Our model room is now fully furnished—exactly as we envisioned it. The materials, colors, and details come together harmoniously, offering a first glimpse of the future hotel experience. Now, furniture production can begin, and the concept can be implemented throughout the hotel, step by step. We are excited about everything to come and look forward to the next milestones!
December 18, 2025

SNEAK PEEK

Our model room is now fully furnished—exactly as we envisioned it. The materials, colors, and details come together harmoniously, offering a first glimpse of the future hotel experience. Now, furniture production can begin, and the concept can be implemented throughout the hotel, step by step. We are excited about everything to come and look forward to the next milestones!

Things are moving fast on our construction site: the piling work is complete, with nearly 50 piles now in place. Two cranes have been set up, and we are making visible progress on the ground floor as well—the first concrete wall has already been poured. The remaining concrete walls are currently being shuttered and will follow later this December.
December 10, 2025

WE ARE MAKING PROGRESS

Things are moving fast on our construction site: the piling work is complete, with nearly 50 piles now in place. Two cranes have been set up, and we are making visible progress on the ground floor as well—the first concrete wall has already been poured. The remaining concrete walls are currently being shuttered and will follow later this December.

Demolition is complete and the site is ready for the next steps. With the first pile drilling beneath the floor slab, the construction phase has officially begun, and everything is being prepared for the foundation of Hotel 6000.
24. September 2025

LET'S GO

Demolition is complete and the site is ready for the next steps. With the first pile drilling beneath the floor slab, the construction phase has officially begun, and everything is being prepared for the foundation of Hotel 6000.

Demolition work is nearing completion. Only a few sections of the building remain to be removed before we can begin the construction phase.
August 28, 2025

GET RID OF IT

Demolition work is nearing completion. Only a few sections of the building remain to be removed before we can begin the construction phase.

Dismantling is in full swing. Fortunately, the weather is cooperating, which is helping to speed up the demolition progress.
July 21, 2025

DISMANTLING

Dismantling is in full swing. Fortunately, the weather is cooperating, which is helping to speed up the demolition progress.

Demolition of the existing building began today, officially marking the start of construction for Hotel 6000.
May 28, 2025

GET STARTED

Demolition of the existing building began today, officially marking the start of construction for Hotel 6000.